CITY OF EUGENE -FREDERICK CT. STORM DRAINAGE SYSTEM <br /> URS Greiner Woodward Clyde Project #52-945042ND.02 <br /> Eugene Design Task <br /> Project Manager: Mike Fowler <br /> Progress Report 4 <br /> Peripd beginning December 4, 1999 and December 31, 1999 <br /> I. Budget Status Total Previous Expenditures: $3,052 <br /> Total Current Invoice: $2,813 <br /> Total Billed: $5,865 <br /> Contract Amount: $18,550 <br /> ~I. Project Work . Completed the analysis of the capacity of the system using the 10-year <br /> Completed design storms under existing and future land use conditions. <br /> • Prepared a summary of the flood control problem identification to the City. <br /> III. Work to be • Submit the flood control technical memorandum to the City. <br /> Completed during . Coordinate with the City and complete the preliminary design of drainage <br /> the Next Period improvements for the 34`h Avenue drainage system. <br /> IV. Outstanding None. <br /> Requests for <br /> Information <br /> <br /> C:\TEMP\PR4.DOC 01-1 1-QO <br /> <br />