. + <br /> CITY OFEUGENE - FREDERICK CT. STORM DRAINAGE SYSTEM <br /> URS Greiner Woodward Clyde Project #52-945042ND.02 <br /> Eugene Design Task <br /> Project Manager: Mike Fowler <br /> Progress Report 8 <br /> Period beginning March 25, 2000 and ending April 21, 2000 <br /> I. Budget Status Total Previous Expenditures: $15,000 <br /> Total Current Invoice: $268 <br /> Total Billed: $15,268 <br /> Contract Amount: $18,550 <br /> II. Project Work • Provided the updated hydrologic subbasin information for the 34`h Ave. to Sharon <br /> Completed Budzier. <br /> • Provided Brain Genovese the HGL information for the storm segments along 29~' <br /> Ave. <br /> III. Work to be • Provide additional technical support to the City, as needed. <br /> Completed during <br /> <br /> ~r,r the Next Period <br /> IV. Outstanding None. <br /> Requests for <br /> Information <br /> C:~TEMPIPR8.DOC O5-O 1-OO <br /> <br />