|
Run Date: 08~b6/2007 10:39:48 Page 2
<br /> City of Eugene
<br /> 1 Contract Preliminary Progress Payment
<br />
<br /> ' Payment No 010 Final Pay
<br /> Contractor: DELTA CONST. Original Contract: $459,996.00
<br /> Job k: 93-003951 Current Amount: $455,783.74
<br /> Contract No: 2007-00009 Contract Award Date: 08/14/2006
<br /> PO 8: 2007100103 Completion Date:
<br /> Assessable: No
<br /> Current Contract Estimated Payment Cumulative Totals $ Complete
<br /> Line Description Last Chng Ord Unit Price Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br /> UPPER AMAZON STRBAM RBSTORATION
<br /> GBNHRAL
<br /> 0000 Liquidated Damages ($310.00) DAY 0.000 $0.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 0010 MOBILIZATION $108,259.00 LUMPSUM 1.000 $108,259.00 0.100 $10,825.90 1.000 $108,259.00 M 100.00
<br /> 0020 CLEARING & GRUBBING $24,760.00 LUMPSUM 1.000 $24,760.00 0.000 $0.00 1.000 $24,760.00 100.00
<br /> 0030 TEMP PROTECTN/DIRECTN $8,620.00 LUMPSUM 1.000 $8,620.00 0.100 $862.00 1.000 $8,620.00 100.00
<br /> 0040 EROSION CONTROL $4,000.00 LUMPSUM 1.000 $4,000.00 0.400 $1,600.00 1.000 $4,000.00 100.00
<br /> 0050 DEWATERING $4,000.00 LUMPSUM 1.000 $4,000.00 0-000 $0.00 1.000 $4,000.00 100.00
<br /> 0060 FENCE (CONSTUCTION) $3.00 LINFT 1,500.000 $4,500.00 0.000 $0.00 812.100 $2,436.30 54.00
<br /> 0070 EXCAVATION $18.00 CUYD 1,500.000 $27,000.00 0.000 $0.00 1,866.000 $33,588.00 124.00
<br /> 0080 RIP RAP LOOSE, PLACED $223.00 TON 30.000 $6,690.00 0.000 $0.00 30.100 $6,712.30 100.00
<br /> 0090 BOULDERS, Weir/wall Rock 003 $0.00 TON 0.000 $0.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 0100 FABRIC, GBOTBETILH $2.00 SQYD 350.000 $700.00 0.000 $0.00 456.440 $912.88 130.00
<br /> 0110 EROSION MATTING $6.00 SQYD 1,200.000 $7,200.00 0,000 $0.00 723.790 $4,342.74 60.00
<br /> 0120 MULCH COMPOST $25.00 CUYD 65.000 $1,625.00 7.330 $183.25 97.330 $2,433.25 150.00
<br /> 0130 MULCH BARK $25.00 CUYD 150.000 $3,750.00 0.000 $0.00 18.750 $468.75 13.00
<br /> 0140 CHANNEL ROCK 002 $65.00 TON 230.000 $14,950.00 0.000 $0.00 59.970 $3,898.05 26.00
<br /> 0150 TREE TOPPED/CUT $300.00 EACH 12.000 $3,600.00 0.000 $0.00 14.000 $4,200.00 117.00
<br /> 0160 PREFAB METAL FOOT BRIDGE $24,658.00 LUMPSUM 1.000 $24,658.00 0.000 $0.00 1.000 $24,658.00 100.00
<br /> 0170 PRECAST 6X6 BOX CULVERT TAPER $6,066.00 EACH 2.000 $12,132.00 0.000 $0.00 2.000 $12,132.00 100.00
<br /> O1B0 BOX CULVERT $796.00 LINFT 56.000 $44,576.00 0.000 $0.00 56.000 $44,576.00 100.00
<br /> 0190 DRN PIPE RCCP 42" DL= $262.00 LINFT 144.000 $37,726.00 0.000 $0.00 126.000 $33,012.00 88.00
<br /> 0200 MH 42"-54" PIPE - STM $5,055.00 EACH 1.000 $5,055.00 0.000 $0.00 1.000 $5,055.00 100.00
<br /> 0210 CONNECT EXIST PIPE - STM $1,200.00 EACH 1.000 $1,200.00 0.000 $0.00 1.000 $1,200.00 100.00
<br />
<br />
|