CITY OF EUGENE <br /> ` ~ DEPARTMENT OF PUBLIC WORKS <br /> ENGINEERING DIVISION <br /> Change Order Job # 4091 <br /> Contract # 2006-02 <br /> CONTRACTOR: Eugene Sand & Gravel Change Order # 2 <br /> (ADDRESS) P.O. Box 1067 Date: 10/07105 <br /> Eugene, OR 97440 CAMS Date: <br /> Reviewed by: Date: <br /> PROJECT: Judkins Point north widening of roadway along Glenwood Boulevard Inspector: Ray Remmers <br /> from the Interstate Highway north approximately 700', widening Exit 191 <br /> on/off ramp from Glenwood Blvd. east approximately 200' Proj. Mgr. John Bonham <br /> Principal Eng. Michelle Cahill <br /> <br /> You are directed to make the following changes in this contract: <br /> Contract <br /> Item <br /> No. <br /> 210 CREDIT • ATTACH GUARD RAIL TO BRIDGE BARRIER <br /> 270 ADD CRASH TERMINAL TYPE GUARD RAIL END TREATMENTS <br /> This changes the bid items as follows: <br /> Contract Contract <br /> Item Time Quantity Unit Amended Net <br /> No. Item Change Units Cost Amount Chan a Change <br /> 210 CREDTf ATTACH GUARD RAIL TO Ori final 2.00 EA 3 600.00 7 200.00 ($922.60) <br /> BRIDGE BARRIER Revised 2.00 EA 3 138.70 6 277.40 <br /> Amended 0.00 $0.00 $0.00 $0.00 <br /> 270 CRASH TERMINALS, GUARD RAIL END Ori final 0.00 0.00 0.00 $0.00 <br /> TREATMENT Revised 0.00 0.00 0.00 <br /> Amended 1.00 LS $2143.80 $2143.80 $2143.80 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 $0.00 $0.00 $0.00 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 $0.00 0.00 $0.00 <br /> Ori final 0.00 O.OD 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 $0.00 $0.00 $0.00 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 $0.00 $0.00 0.00 <br /> original contract work days are 45.0 da s <br /> contract time change this C.O o.o da s <br /> e contract time change by previous C.O.'s o.o da s <br /> The new contract work da s are 45.0 da s <br /> The original contract sum was 5176,371.20 <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> Net change by previous change order 51ss.25 <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> Net change due to amendment by previous change order 51,250.00 <br /> The contract sum prior to this change order was 5177,807.45 <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> Thus change cyder will change contract sum by this amount ~ ~ " <br /> The new contract net change sum (5736.35) <br /> The new contract amendment sum 53,393.80 <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> The new contract sum including this change order will be 5179,DZ8.s5 <br /> Percents a of on final contract 1.51 °b <br /> N CHANGE DUE TO AMENDMENTS 1.92% <br /> or al y: <br /> City Engineer Prime Contractor Third Party <br /> ~~/a~s~ <br /> Date Date Date <br /> CONTRACTOR ~ OFFICE FILE O PURCHASING/CRO ' <br /> Q~FORMS~PROJECTICONSTIREVISED CHANGE ORDER.XLS <br /> <br />