• t , <br /> <br /> ~MA20N HEADWATERS TRAIL #4180 <br /> Chanae: Item 3 -Revised Routing <br /> Reason: Additional raised trail bed to accomidate new third bridge location. Third bridge location changed at <br /> geotechnical engineer's recommendation. Reimbursement should be journal entried back to this project once GJN is <br /> set up for third bridge project. <br /> Construction 8~ Contract Costs <br /> Item Quanti Units Unit Price Amount <br /> 220 Clearing & Grubbing 195 M $7.00 $1,365.00 <br /> 230 Excavation 195 M $5.00 $975.00 <br /> 240 Grade Dip 0 EACH $40.00 $0.00 <br /> 250 Agg. Surfacing 34.8 M3 $130.00 $4,524.00 <br /> 260 Retainers -Treated Poles 358 M $12.00 $4,296.00 <br /> 270 Geosynthetics -Non-woven 218 M2 $4.00 $872.00 <br /> 280 Split Rail Fence 16 LF $25.00 $400.00 <br /> TOTAL Item 3 Revised $12,432.00 <br /> Item 3 Original 9 843.20 <br /> Net Change $2,588.80 <br /> Adminstrative Costs <br /> Person Date Time Hr Work Cost/ Hr Amount <br /> Adam Steffen 3/17/2005 2 Field layout and stationing $79 $158 <br /> Larry Wilson 3/17/2005 2 Field layout and stationing $25 $50 <br /> Adam Steffen 3/17/2005 2 Admin. -New work summary ~ $79 $158 <br /> Change letter <br /> Adam Steffen 3/18/2005 2 Admin. -Change pricing, materials $79 $158 <br /> review, and Change letter <br /> $0 <br /> $0 <br /> $0 <br /> $0 <br /> TOTAL $524 <br /> Total Construction & Contract Costs $2,588.80 <br /> Total Adminstration Costs ~ $524 <br /> Total Change Costs $3,11280 <br /> <br />