<br /> Run Date: U9/08/2005 10:43:09 Page 9
<br /> City of Eugene
<br /> ~ Contract Preliminary Progress Payment
<br /> Payment No : 015
<br /> Contractor: WILDISH CONST. Original Contract: $16,589,175.71
<br /> Job 93-004183 Current Amount: $16,816,665.33
<br /> Contract No: 2004-00024 Contract Award Date: 06/07/2004
<br /> PO 2004100581 Completion Date: 10/15/2006
<br /> Assessable: No
<br /> Current Contract Estimated Payment Cumulative Totals ~ Complete
<br /> Line Description Last Chng Ord Uait Prics Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br /> 1360 EXCAVATION, UNCLASSIFIED $3.50 CUYD 15,600.000 $54,600.00 2,085.000 $7,297.50 17,300.000 $60,550.00 111.00
<br /> 1370 BORROW $8.00 CUYD 11,100.000 $88,800.00 0.000 $0.00 11,100.000 $88,800.00 100.00
<br /> 1380 SUBBASE COURSE (P-154) $3.50 SQYD 29,497.000 $103,239.50 0.000 $0.00 29,000.000 $101,500.00 98.00
<br /> 1390 fiROSION MAT $1.45 SQYD 9,200.000 $13,340.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1400 EMERGENCY BROSION CONTROL MOHI $400.00 EACH 2.000 $800.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1410 REMOVE EXISTING ELECTRICAL VAU $2,000.00 LUMPSUM 1.000 $2,000.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1420 REMOVE STORM SEWER, UNDER 30 I $9.00 LINFT 999.000 $8,991.00 400.000 $3,600.00 900.000 $8,100.00 90.00
<br /> 1430 REMOVE STORM SEWER INLET $125.00 EACH 16.000 $2,000.00 7.000 $875.00 15.000 $1,875.00 94.00
<br /> 1440 REMOVE VASI FOUNDATION $750.00 SBT 2.000 $1,500.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1450 CRUSHED AGGREGATE BASB COURSE $12.00 TON 1,652.000 $19,824.00 500.000 $6,000.00 1,500.000 $18,000.00 91.00
<br /> 1460 CEMENT TREATED BASE COURSH, 12 $11.00 SQYD 40,572.000 $446,292.00 9,572.000 $105,292.00 40,572.000 $446,292.00 100.00
<br /> 1470 HITUMZNOUS CONCRETE PAVEMENT ( $30.00 TON 11,440.000 $343,200.00 10,404.210 $312,126.30 11,878.980 $356,369.40 104.00
<br /> 1480 HITUNINOIIS PAVENHNT QIIALITY CO $0.50 TON 6,445.000 $3,222.50 10,404.210 $5,202.11 11,878.980 55,939.49 184.00
<br /> 1490 PAVEMENT MARKING, WHITE, TYPE $0.43 SQFT 3,510.000 $1,509.30 2,880.000 $1,238.40 3,000.000 $1,290.00 85.00
<br /> 1500 PAVEMENT MARKING, YELLOW, TYPE $0.43 SQFT 5,566.000 $2,393.38 5,000.000 $2,150.00 5,000.000 $2,150.00 90.00
<br /> 1510 PAVEMENT MARKING, GRBEN, TYPE $0.43 SQFT 7,734.000 $3,325.62 0.000 $0.00 0.000 $0.00 0.00
<br /> 1520 RBPLECTIVE MBDIA, TYPE 1, GRAD $0.29 POUND 1,832.000 $531.28 1,500.000 $435.00 1,500.000 $435.00 82.00
<br /> 1530 OBLITSRATB EXISTING MARKING $1.25 SQPT 1,800.000 $2,250.00 1,700.000 $2,125.00 1,700.000 $2,125.00 94.00
<br /> 1540 SAWCUTTING BITUMINOUS PAVEMENT $2.50 LINFT 4,434.000 $11,085.00 610.000 $1,525.00 1,000.000 $2,500.00 23.00
<br /> 1550 MILLING ASPHALT, 0"-3" $1.00 SQYD 19,650.000 $19,650.00 0.000 $0.00 17,335.000 ~ $17,335.00 BS.00