<br /> Run Date: 12/05/2006 10:08:00 Page 9
<br /> City of Eugene
<br /> Contract Preliminary Progress Payment
<br /> Payment No 032
<br /> Contractor: WZLDISH CONST. Original Contract: $16,589,175.71
<br /> Job 93-004183 Current Amount: $17,810,653.07
<br /> Contract No: 2004-00024 Contract Award Date: 06/07/2004
<br /> PO 2004100581 Completion Date: 10/15/2006
<br /> Assessable: No
<br /> Current Contract Estimated Payment Cumulative Totals 8 Complete
<br /> Line Description Last Chng Ord Unit Price Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br /> 1360 EXCAVATION, UNCLASSIFIED $3.50 CUYD 15,600.000 $54,600.00 0.000 $0.00 17,300.000 $60,550.00 111.00
<br /> 137o BoRROw $s.oo cuYD ll,loo.ooo $ee,eoo.oo o.ooo So.oo o.ooo So.oo o.oo
<br /> 1380 SUBBASE COURSE (P-154) $3.50 SQYD 29,497.000 $103,239.50 0.000 $0.00 29,497.000 $103,239.50 100.00
<br /> 1390 EROSION MAT $1.45 SQYD 9,200.000 $13,340.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1400 EMERGENCY EROSION CONTROL MOBZ _ $400.00 EACH 2.000 $800.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 1410 REMOVE EXISTING ELECTRICAL VAU $2,000.00 LUMPSUM 1.000 $2,000.00 0.000 $0.00 1.000 $2,000.00 100.00
<br /> 1420 REMOVE STORM SEWER, UNDER 30 I $9.00 LINFT 999.000 $8,991.00 0.000 $0.00 950.000 $6,550.00 95.00
<br /> 1430 REMOVE STORM SEWER INLET $125.00 EACH 16.000 $2,000.00 0.000 $0.00 15.000 $1,875.00 94.00
<br /> 1440 REMOVE VASI FOUNDATION $750.00 SET 2.000 $1,500.00 0.000 $0.00 2.000 $1,500.00 100.00
<br /> 1450 CRUSHED AGGREGATE BASE COURSE $12.00 TON 1,652.000 $19,824.00 0.000 $0.00 1,652.000 $19,824.00 100.00
<br /> 1460 CEMENT TREATED BASE COURSE, 12 $11.00 SQYD 40,572.000 $446,292.00 0.000 $0.00 40,572.000 $446,292.00 100.00
<br /> 1470 BITUMINOUS CONCRETB PAVEMENT ( $30.00 TON 11,440.000 $343,200.00 0.000 $0.00 12,845.050 $385,351.50 112.00
<br /> 1480 BITUMINOUS PAVENBNT QIIALITY CO $0.50 TON 6,445.000 $3,222.50 0.000 $0.00 12,845.050 $6,422.53 199.00
<br /> 1490 PAVEMENT MARKING, WHITE, TYPE $0.43 SQFT 3,510.000 $1,509.30 0.000 $0.00 3,300.000 $1,419.00 94.00
<br /> 1500 PAVEP03N'P MARKING, YELLOW, TYPE $0.43 SQFT 5,566.000 $2,393.38 0.000 $0.00 5,400.000 $2,322.00 97.00
<br /> 1510 PAVHMENT MARKING, GREEN, TYPE $0.43 SQFT 7,734.000 $3,325.62 0.000 $0.00 0.000 $0.00 0.00
<br /> 1520 REPLHCTIVE MEDIA, TYPH 1, GRAD $0.29 POUND 1,832.000 $531.28 0.000 $0.00 1,800.000 $522.00 95.00
<br /> 1530 OBLITERATE BZISTING MARKING $1.25 BQPT 1,800.000 $2,250.00 0.000 $0.00 2,517.000 $3,146.25 140.00
<br /> 1540 SAWCUTTING BITUMINOUS PAVEMENT $2.50 LINFT 4,434.000 $11,085.00 0.000 $0.00 3,000.000 $7,500.00 68.00
<br /> 1550 MILLING ASPHALT, 0"-3" $1.00 SQYD 19,650.000 $19,650.00 0.000 $0.00 19,650.000 $19,650.00 100.00