CITY OF EUGENE D,~~ ~ <br /> DEPARTMENT OF PUBLIC WORKS ~ <br /> ENGINEERING DIVISION ~ <br /> Change Order Job# alss <br /> Contract # 2005-21 <br /> CONTRACTOR: Wildish Construction Change Order # 1 <br /> (ADDRESS) P.O. Box 7428 Date: 04!20!05 <br /> Eugene OR 97401-0428 CAMS Date: <br /> Reviewed b : Date: <br /> PROJECT: PPP 28TH AVENUE PAVING Inspector: D Reubell p~_ <br /> FRIENDLY TO CITY VIEW Const. Mana er P Dickinson <br /> Proj. Mgr. M Rodrigues ~S <br /> Principal Eng. P Klope <br /> <br /> You are directed to make the following changes in this contract: <br /> Contract <br /> Item <br /> No. <br /> 60 CITY PROVIDED SPECIAL INFO SIGNS <br /> 270 INSTALL SPECIAL INFO SIGNS 5 WORKING DAYS PRIOR TO ANY OTHER CONSTRUCTION BEGINNING <br /> This changes the bid items as follows: <br /> Contract Contract <br /> Item Time Quantity Unit Amended Net <br /> No. Item Chan a Units Cost Amount Chan a Change <br /> Ori final 4.00 275.00 1100.00 $550.00 <br /> 60 City provided spec info signs 0 Revised 6.00 275.00 1650.00 <br /> Amended 0.00 0.00 0.00 ;0.00 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> 270 INSTALL SPEC INFO SIGNS 5 Amended 0.00 0.00 ¢0.00 0.00 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 ;0.00 $0.00 0.00 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 0.00 ¢0.00 $0.00 <br /> Ori final 0.00 0.00 0.00 $0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 0.00 0.00 0.00 <br /> Ori final 0.00 0.00 0.00 ¢0.00 <br /> Revised 0.00 0.00 0.00 <br /> Amended 0.00 ¢0.00 0.00 0.00 <br /> riginal contract work days are 20.o da s <br /> The contract time change this C.O 5.0' da s <br /> The contract time change by previous C.O.'s o.o da s <br /> The new contract work da s are 25.o da s <br /> The original contract sum was 331a,a1a.7o <br /> Net change by previous change order 30.00 <br /> Net change due to amendment by previous change order 30.00 <br /> s,.. <br /> The contract sum prior to this change order was -'"--~'+~.~4~`~= <br /> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br />. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . <br /> This change order will change contract sum by this amount 3550.00 <br /> The new contract net change sum 3550.00 <br /> The new contract amendment sum 30.00 <br /> The new contract sum including this change order will be 3318,984.70 <br /> Percents a of on final contract 0.1796 <br /> 0.00% <br /> NET RANGE DUE TO AMENDMENTS <br /> pval y: <br /> C' Engineer Prime Contractor Third Party <br /> Date Dat Date <br /> CONTRACTOR ~ OFFICE FILE ~ PURCHASING/CRO <br /> Q~FORMSIPROJECT\CONST~REVISED CHANGE ORDER.XLS , <br /> <br />