<br /> Run Date: 07/05/2005 12:22:02 City of Eugene
<br /> Contract Preliminary Progress Payment
<br /> Payment No 002
<br /> Contractor: WILDISH CONST. Original Contract: $318,414.70
<br /> Current Amount: $318,964.70
<br /> Job 93-004195
<br /> Contract Award Date: 04/07/2005
<br /> Contract No: 2005-00021 Completion Date: 06/30/2005
<br /> p0 2005050414
<br /> Assessable: No
<br /> Current Contract fistimated Payment Cumulative Totals t Complete
<br /> Last Chng Ord Uait Price Unit Measure Quantity Amount Quantity Amount Quantity Amount
<br /> Line Description
<br /> PPP 2005 - W. 28TH FROM FRIHNDLY TO CITY VIBW
<br /> 28th Avenue from Friendly to City View
<br /> 0000 Liquidated Damages ($310.00) DAY 0.000 $0.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 0010 MOBILIZATION $29,000.00 LUMPSUM 1.000 $29,000.00 0.500 $14,500.00 1.000 $29,000.00 100.00
<br /> 0020 TEMPORARY WORK ZONE TRAFFIC CO $11,000.00 LUMPSUM 1.000 $11,000.00 0.670 7,370.00 1.000 $11,000.00 100.00
<br /> 0030 EROSION CONTROL $3,300.00 LUMPSUM 1.000 $3,300.00 0.670 $2,211.00 1.000 $3,300.00 100.00
<br /> 0040 FLAGGING, POLICE $65.00 HOUR 50.000 $3,250.00 0.000 $0.00 0.000 $0.00 0.00
<br /> 0050 FLAGGING $36.00 HOUR 500.000 $18,000.00 521.500 $18,774.00 572.000 $20,592.00 114.00
<br /> 0060 CITY PROVIDED SPEC INFO SIGNS 001 $275.00 EACH 6.000 $1,650.00 0.000 $0.00 6.000 $1,650.00 100.00
<br /> 0070 LEVEL 2, 1/2 IN DENSfi HMAC $36.50 TON 1,646.000 $60,079.00 1,679.710 $61,309.42 1,679.71D $61,309.42 M 102.00
<br /> 0080 LEVEL 2, 3/4 IN DSNSS NMAC $95.00 YON 218.000 $9,810.00 234.710 $10,561.95 300.120 $13,505.40 138.00
<br /> 0090 LEVEL 3, 1/2 IN DENSE HMAC $39.00 TON 1,386.000 $54,054.00 1,553.640 $60,591.96 1,553.640 $60,591.96 M 112.00
<br /> 0100 LEVEL 3, 3/4 IN DENSE HMAC $38.00 TON 515.000 $19,570.00 288.820 $10,975.16 288.820 $10,975.16 56.00
<br /> 0110 COLD PLANS PVMT RBMOVAL, 0-2 I $0.25 S FT 85 415.000 $21,353.75 90,146.750 $22,536.69 90,146.750 $22,536.69 106.00
<br /> 0120 PAVEMBNT REMOVAL $0.70 SQFT 17,728.000 $12,409.60 11,377.500 $7,964.25 11,377.500 $7,964.25 64.00
<br /> 0130 SURFACING STABILIZATION $52.00 CUYD 468.000 $29,336.00 281.850 $14,656.20 408.240 $21,228.48 87.00
<br /> 0140 TEMPORARY STRIPING 600.00 LUMPSUM 1.000 $600.00 1.000 $600.00 1.000 $600.00 100.00
<br /> 0150 TfiERMOPAST, NON-PROF, 120 MIL, $18,000.00 LUMPSUM 1.000 $18,000.00 1.000 $18,000.00 1.000 $18,000.00 100.00
<br /> 0160 PVMT LEGEND, TYPE A-lor A-2: B $110.00 EACH 4.000 $440.00 4.000 $440.00 4.000 $440.00 100.00
<br /> 0170 PAVEMENT LINE, TYPE A-1 or A-2 $3.00 SQFT 265.000 795.00 288.500 $865.50 288.500 $865.50 109.00