Eugene Water & Electric Board <br /> - - <br /> 500 East 4th Avenue /Post Office Box 10148 <br /> EWEB Eugene, Oregon 97440-2148 <br /> 541-484-2411 Fax 541-484-3762 <br /> <br /> ~irr February 1, 2007 <br /> Joe Ramirez <br /> City of Eugene <br /> 244 E. Broadway <br /> Eugene Oregon 97401 <br /> Subject: COURTHOUSE DISTRICT TRANSPORTATION 1MPROVEMENTS- <br /> Phase 2 Request for Converting Aerial Electrical Power System from OH <br /> to UG Wires, Conduits and Vaults, City Project #4237. <br /> Dear Joe, <br /> I have enclosed the billing for conversion of the existing overhead electric lines to <br /> underground per the request from the City of Eugene. In addition, I have included an <br /> Electric Underground Extension Agreement for signature, along with the EWEB <br /> Construction Drawing. ~1 ' ~ <br /> ~ ~ <br /> Cost Breakdown as follows: ~ ~i <br /> J <br /> Electric Cost Estimate $ 08,178.00 ~R ~ <br /> Joint Electric Substructure Costs $ 41,169.62 ~ ~;1 <br /> Joint Qwest Substructure Costs $ 21,635.2 ~ ~o fl~ ~ ~ <br /> Joint Comcast Substructure Costs $ 24,950.157 /r%' ~ ? <br /> Total Cost to City $ 135,933.04 ' <br /> In regards to the substructure costs, every effort has been made to determine an accurate <br /> estimate based on known subsurface conditions, if unforeseen conditions arise during <br /> excavation that result in additional work outside of the project bid amounts, EWEB <br /> reserves the right to issue a "Change Order" that will affect the billing amounts. <br /> If you have any questions regarding the Electric Cost Estimate above, please do not <br /> hesitate to call me at 341-8523. <br /> If you have questions regarding the Substructure Costs, please call Rick Sitowski, EWEB <br /> Utility Estimator, 484-2411 ext. 3969. <br /> Thank You, <br /> . <br /> Steve Buzalsky <br /> EWEB Electric Distribution Technician III <br /> Cc: Michelle Cahill - City of Eugene Attachments: Agreement (2) <br /> Greg Gardner -EWEB Drawing D-24340-E <br /> File Cost Estimate <br /> <br />