Courthouse Transportaion District Improvements, Phase 2
<br /> Grading, Drainage, Structure, Paving, Illumination, Signals and Roadside Development
<br /> City of Eugene
<br /> Engineer's Cost Estimate (Final) 2-15-07
<br /> Spec Item Bid Unit Est. Unit Quantity Unit Cost Total Cost
<br /> No. No.
<br /> TEMPORARY FEATURES AND APPURTENANCES
<br /> 00210 10 Mobilization Lump Sum Lump Sum All Lump Sum $ 391,100.00
<br /> 00225 20 Temporary Protection and Direction of Traffic Lump Sum Lump Sum All Lump Sum $ 60,000.00
<br /> 00225 30 Temporary Signs Sq. Ft. Sq. Ft. 1,173.2 $ 14.00 $ 16,424.80
<br /> 00225 40 Temporary Barricades, Type II Each Each. 20 $ 50.00 $ 1,000.00
<br /> 00225 50 Temporary Barricades, Type III Each Each 44 $ 130.00 $ 5,720.00
<br /> 00225 60 Temporary Plastic Drums Each Each 200 $ 45.00 $ 9,000.00
<br /> 00225 70 Temporary Striping Ft. Ft. 300.0 $ 1.00 $ 300.00
<br /> 00225 80 Sequential Arrow Signs Each Each 2 $ 3,000.00 $ 6,000.00
<br /> 00225 90 Flaggers Hour Hour 2,500 $ 38.00 $ 95,000.00
<br /> 00280 100 Erosion Control Lump Sum Lump Sum All Lump Sum $ 8,000.00
<br /> 00280 110 Construction Entrances Each Each 3 $ 1,500.00 $ 4,500.00
<br /> 00280 120 Inlet Protection, Type 3 Each Each 48 $ 75.00 $ 3,600.00
<br /> 00280 130 Inlet Protection, Type 4 Each Each 102 $ 75.00 $ 7,650.00
<br /> 00280 140 Sediment Fence, Unsupported Ft. Ft. 750.0 $ 3.50 $ 2,625.00
<br /> 00280 150 Matting, Type D Sq. Ft. Sq. Ft. 5,000.0 $ 0.30 $ 1,500.00
<br /> 00290 160 Pollution Control Plan Lump Sum Lump Sum All Lump Sum $ 3,000.00
<br /> ROADWORK
<br /> 00310 170 Removal of Structures and Obstructions Lump Sum Lump Sum All Lump Sum $ 30,000.00
<br /> 00310 180 Removal of Building Lump Sum Lump Sum All Lump Sum $ 4,000.00
<br /> 00310 190 Removal of Manholes Each Each 1 $ 750.00 $ 750.00
<br /> 00320 200 Clearing and Grubbing Lump Sum Acre 0.5 $ 10,000.00 $ 5,000.00
<br /> 00330 210 General Excavation Cu. Yd. Cu. Yd. 6,900.0 $ 19.00 $ 131,100.00
<br /> 00331 220 Subgrade Stabilization Cu. Yd. Cu. Yd. 1,000.0 $ 35.00 $ 35,000.00
<br /> 00332 230 19 Inch Surfacing Stabilization Sq. Yd. Sq. Yd. 145.0 $ 30.00 $ 4,350.00
<br /> 00350 240 Subgrade Geotextile Sq. Yd. Sq. Yd. 13,700.0 $ 1.00 $ 13,700.00
<br /> DRAINAGE AND SEWERS
<br /> 00445 250 6 Inch Sanitary Sewer Pipe, 5 Ft Depth Ft. Ft. 320.0 $ 55.00 $ 17,600.00
<br /> 00445 260 8 Inch Sanitary Sewer Pipe, 5 Ft Depth Ft. Ft. 455.0 $ 54.00 $ 24,570.00
<br /> 00445 270 10 Inch Storm Sewer Pipe, 5 Ft Depth Ft. Ft. 271.0 $ 38.00 $ 10,298.00
<br /> 00445 280 12 Inch Storm Sewer Pipe, 5 Ft Depth Ft. Ft. 1,703.0 $ 42.00 $ 71,526.00
<br /> 00445 290 12 Inch Storm Sewer Pipe, 10 Ft Depth Ft. Ft. 346.0 $ 70.00 $ 24,220.00
<br /> 00445 300 18 Inch Storm Sewer Pipe, 10 Ft Depth Ft. Ft. 46.0 $ 80.00 $ 3,680.00
<br /> 00470 310 Concrete Sanitary Sewer Manholes Each Each 2 $ 2,700.00 $ 5,400.00
<br /> 00470 320 Concrete Manholes, 48 Inch Each Each 8 $ 2,700.00 $ 21,600.00
<br /> 00470 330 Concrete Manholes, 60 Inch Each Each 2 $ 3,900.00 $ 7,800.00
<br /> 00470 340 Concrete Manholes, Water Quality Each Each 2 $ 15,000.00 $ 30,000.00
<br /> 00470 350 Concrete Inlets, Type C.O.E Grate Each Each 5 $ 1,050.00 $ 5,250.00
<br /> 00470 360 Concrete Inlets, Type C.O.E Curb Each Each 21 $ 1,100.00 $ 23,100.00
<br /> 00480 370 Drainage Curbs Ft. Ft. 496.0 $ 12.00 $ 5,952.00
<br /> 00490 380 Adjusting Boxes Each Each 17 $ 250.00 $ 4,250.00
<br /> 00490 390 Connection to Existing Structures Each Each 16 $ 950.00 $ 15,200.00
<br /> 00490 400 Adjusting Inlets Each Each 4 $ 100.00 $ 400.00
<br /> 00490 410 Minor Adjustment of Manholes Each Each 30 $ 900.00 $ 27,000.00
<br /> 00490 420 Major Adjustment of Manholes Each Each 6 $ 1,100.00 $ 6,600.00
<br /> 00490 430 Abandon Manholes Each Each 1 $ 400.00 $ 400.00
<br />
<br /> 00490 440 Electronic Service Location Each Each 8 $ 250.00 $ 2,000.00
<br />
<br /> 00496 450 Emergency Overflow Each Each 5 $ 1,000.00 $ 5,000.00
<br /> 00496 460 Flow Spreaders Each Each 21 $ 100.00 $ 2,100.00
<br />
<br />
|