GJN 4264 Contractor: <br /> 43rd & Donald SW Upgrade Wildish <br /> Req: 2006050498 Contract #2006-00029 <br /> Project Manager: Matt Rodrigues x6036, PWE <br /> PO # Date Amount Contract Contin enc Chan a Orders <br /> 2006100466 16-Jun-06 $1,118,136.00 $ 1,016,487.00 $ 101,649.00 <br /> col 8/10/2006 $ 725.00 $ (725.00) 725.00 <br /> cot 9/6/2006 $ 10,428.11 10,428.11 <br /> co3 12/6/2006 $ 1,195.02 $ (1,195.02) 1,195.02 <br /> coa 1/12/2007 $ 3,769.94 $ (3,769.94) 3,769.94 <br /> cos 4/9/2007 $ 8,264.12 $ (8,264.12) 8,264.12 <br /> cos 6/28/2007 $ 84,312.32 84,312.32 <br /> Totals $1,226,830.51 $ 1,016,487.00 $ 87,694.92 $ 108,694.51 <br /> Payments Purchase Order Contract <br /> # Date Amount Balance Balance Retaina e <br /> $ 1,212,876.43 $ 1,125,181.51 <br /> 1 8/10/2006 $ 340,476.00 $ 872,400.43 $ 784,705.51 <br /> 2 9/11/2006 $ 534,034.35 $ 338,366.08 $ 250,671.16 <br /> 3 10/11 /2006 $ 211,496.07 $ 126,870.01 $ 39,175.09 <br /> 4 11/9/2006 $ 4,380.00 $ 122,490.01 $ 34,795.09 <br /> 5 12/7/2006 $ 1,195.02 $ 121,294.99 $ 33,600.07 <br /> 6 1/12/2007 $ 3,769.94 $ 117,525.05 $ 29,830.13 <br /> 7 3/8/2007 $ 3,699.43 $ 113,825.62 $ 26,130.70 <br /> 8 4/11/2007 $ 8,264.12 $ 105,561.50 $ 17,866.58 <br /> 9 8/7/2007 $ 84,312.32 $ 21,249.18 $ (66,445.74) <br /> $1,191,627.25 $ _ <br /> **When C04 came the summary of previous changes orders and new contract total were not correct. PWE <br /> did not include C03 in the amounts. Lynn will fix and have resigned when they process C05 next month. <br /> PWE will have vendor resign and forward new approved copy to PWA. 1.12.07 Ddc <br /> **Per Lynn 1.12.07 C06 to be coming soon up to $100k. <br /> <br /> **C06 came in as $84,312.32 had Sarah/Mia in purch increase PO by CO via phone conversation. 6.27.07 PWAddc <br /> <br />