DELTA PONDS PARKING LOT ~ ~ ' <br /> COST ESTIMATE DRAFT <br /> November 12, 2004 <br /> NO. ITEM <br /> UNIT QUANTITY UNIT COST TOTAL COST <br /> 1 MOBILIZATION LUMP SUM ALL REQ'D $18,000.00 $18,000.00 <br /> 2 TPDT <br /> LUMP SUM ALL REQ'D $2,500.00 $2,500.00 <br /> 3 EROSION CONTROL LUMP SUM ALL REQ'D $1,000.00 $1,000.00 <br /> 4 REMOVAL OF STRUCTURES LUMP SUM ALL REQ'D $1,500.00 <br /> AND OBSTRUCTIONS $1,500.00 <br /> 5 CLEARING & GRUBBING LUMP SUM ALL REQ'D $3,000.00 <br /> $3,000.00 <br /> 6 GENERAL EMBANKMENT CU. YD 1226.00 <br /> $15.00 $18,390.00 <br /> 7 RIPRAP BASINS EACH 2.00 <br /> $1,000.00 $2,000.00 <br /> 8 12 INCH STORM SEWER PIPE FEET 50.00 <br /> $25.00 $1,250.00 <br /> 9 18 INCH STORM SEWER PIPE FEET 75.00 <br /> $40.00 $3,000.00 <br /> 10 CONCRETE DITCH INLET EACH 1.00 <br /> $800.00 $800.00 <br /> 11 MH 42"-54" PIPE - STM EACH 1.00 <br /> $3,000.00 $3,000.00 <br /> 12 RETAINING WALL, CONVENTIONAL SEGMENTAL SQ.FT. 758.00 <br /> $23.00 $17,434.00 <br /> <br /> 13 1 1/2"-0 DENSE GRADED AGGREGATE BASE TON 220.00 <br /> $10.00 $2,200.00 <br /> <br />