<br /> Run Date: 07,.f21/2006 08:56:25 City of Eugene
<br /> ~ ` Estimate Distribution
<br /> f•
<br /> Estimate: Post Bid
<br /> Job 93-004331 WASTSWATSR RSH 2006 BASINS DC-11,12,13,15, 23 DF14
<br /> Line No. Description Quantity Unit Unit Price Amount
<br /> 0550. TREE PROTECTION FENCING 42.00 FOOT $2.00 $84.00
<br /> 0560. TREE PROTECTION ROOT ZONE EXCAVATION 1.00 EACH $212.00 $212.00
<br /> 0570. CONSTRUCT STD. 4"/6" PVC SERVICE CONNECTION 1.00 EACH $493.00 $493.00
<br /> 0580. CONSTRUCT 6 INCH PVC SADDLE CONNECTION 15.00 EACH $635.00 $9,525.00
<br /> 0590. CONST. 4"/6" PVC SEWER PIPE 489.00 FT $60.00 $29,340.00
<br /> 0600. DYE TEST AND CONNECTION VERIFICATION 17.00 EACH $206.00 $1,802.00
<br /> 0610. LOCATE & MAP EXISTING SERVICE 6.00 EACH $132.00 $792.00
<br /> Total Alternate 1 - 1st Avenue $98,481.00
<br /> Alternate 2 - Elk Avenue
<br /> 0620. MOBILIZATION 1.00 LUMPSUM $530.00 $530.00
<br /> 0630. EROSION CONTROL 1.00 LUMPSUM $318.00 $318.00
<br /> 0640. LANDSCAPING 1.00 EACH $2,120.00 $2,120.00
<br /> 0650. AC PATCH, ALL DEPTHS 2.00 TON $212.00 $424.00
<br /> 0660. CLEANING AND VIDEO INSPECT., PRE & POST 1.00 EACH $1,190.00 $1,190.00
<br /> 0670. SPOT REPAIR, 6 INCH PVC 10.00 FT $175.00 $1,750.00
<br /> 0680. CONSTRUCT 4" FUSED SADDLE CONNECTION 4.00 EACH $741.00 $2,964.00
<br /> 0690. CONST. 4"/6" PVC SEWER PIPE 20.00 FT $64.00 $1,280.00
<br /> 0700. LIMITED ACCESS SERVICE CONNECTION 2.00 EACH $2,650.00 $5,300.00
<br /> 0710. SEWER PIPE 6 INCH HDPE, PIPE BURST 341.00 FT $58.00 $19,778.00
<br /> 0720. CONCRETE MANHOLE, 24 INCH CONCRETE 1.00 EACH $1,590.00 $1,590.00
<br /> Total Alternate 2 - Elk Avenue $37,244.00
<br /> Total WASTSWATSR RSH 2006 BASINS DC-11,12,13,15, 23 DF14 $859,761.00
<br /> WASTSWATSR RSH 2006 BASINS DC-11,12,13,15, 23 DF14 - Other / Direct
<br /> General
<br /> 0010. Contingency 10~ of Contract $85,976.10
<br /> 0020. Advertising 1.00 LUMPSUM $1,000.00 $1,000.00
<br /> 0030. Permits 1.00 LUMPSUM $500.00 $500.00
<br /> 0040. test 1.00 LUMPSUM $7,500.00 $7,500.00
<br /> Total General $94,976.10
<br /> Total WASTSWATSR RSH 2006 BASINS DC-11,12,13,15, 23 DF14 - Other / Direct $94,976.10
<br /> WASTSWATSR RSH 2006 BASINS DC-11,12,13,15, 23 DF14 - Miscellaneous
<br /> General
<br /> 0010. PSF CHARGES TO DATE (FOR EST) 1.00 LUMPSUM $133,637.00 $133,637.00
<br /> 0020. PSF REMAINDER OF PROJ (FOR EST) 1.00 LUMPSUM $120,000.00 $120,000.00
<br /> 0030. AS-CONST. 11MONTH WARRANTY CHARGE 1.00 LUMPSUM $5,000.00 $5,000.00
<br /> Total General $258,637.00
<br /> Total WASTEWATSR RSH 2006 BASINS DC-11,12,13,15, 23 DF14 - Miscellaneous $258,637.00
<br /> Total Post Hid $1,213,374.10