Run Date: 10/25/2005 <br /> City of Eugene <br /> Bid Tabulation <br /> Bid #:2005-000029 <br /> Job No. 93-004330 <br /> 2005 WASTEWATER REPAIRS "TRENCHLESS" BN BASIN PROJECT IS LOCATED PRIMARILY IN THE N.W. PORTION OF EUGENE LOCATED BETWEEN TERRY STREET AND BETHEL DRIVE <br /> FROM ROOSEVELT BOULEVARD TO N. IRWIN <br /> Engineer's Estimate C More Pipe Services Gelco Services <br /> Line <br /> No. Description uantit Unit Unit Price Amount Unit Price Amount Unit Price Amount <br /> General <br /> 10 MOBILIZATION 1 LUMPSUM $10,000.00 $10,000.00 $ 850.00 $ 850.00 $ 5,420.00 $ 5,920.00 <br /> 20 TEMP PROTECTN/DIRECTN 1 LUMPSUM $7,500.00 $7,500.00 $ 4,500.00 $ 9,500.00 $ 3,240.00 $ 3,290.00 <br /> 30 FINAL TV INSPECTION & CLEANING 1 LUMPSUM $11,500.00 $11,500.00 $ 8,400.00 $ 8,400.00 $ 9,330.00 $ 4,330.00 <br /> 90 FLAGGING 80 HOUR $50.00 $4,000.00 $ 70.50 $ 5,640.00 $ 84.00 $ 6,720.00 <br /> 50 MAINLINE GROUTING 8" DIA. 7 EACH $125.00 $875.00 $ 52.00 $ 364.00 $ 941.00 $ 3,087.00 <br /> 60 MAIN LINE GROUTING 15" DIA. 6 EACH $300.00 $1,800.00 $ 72.00 $ 432.00 $ 1,001.00 $ 6,006.00 <br /> 70 MAIN LINE GROUTING 18" DIA. 1 EACH $400.00 $400.00 $ 72.00 $ 72.00 $ 1,150.00 $ 1,150.00 <br /> 80 CONNECTION GROUTING 8" DIA. MAIN 57 EACH $450.00 $25,650.00 $ 500.00 $ 28,500.00 $ 500.00 $ 28,500.00 <br /> 90 CONNECTION GROUTING 10" DIA. MAIN 2 EACH $550.00 $1,100.00 $ 500.00 $ 1,000.00 $ 565.00 $ 1,130.00 <br /> 100 GROUTING SET UP 8" DIA. MAIN 1 EACH $400.00 $400.00 $ 500.00 $ 500.00 $ 345.00 $ 345.00 <br /> 110 GROUTING SET UP 15" & 18" DIA MAINS 3 EACH $750.00 $2,250.00 $ 500.00 $ 1,500.00 $ 395.00 $ 1,035.00 <br /> 120 CONNECTION GROUTING SET UP 8" OR 10" 18 EACH $500.00 $9,000.00 $ 500.00 $ 9,000.00 $ 345.00 $ 6,210.00 <br /> Total: General $74,975.00 $ 60,758.00 $ 67,173.00 <br /> Alternate #1 <br /> 130 MOBILIZATION 1 LUMPSUM $3,500.00 $3,500.00 $ 850.00 $ 850.00 $ 3,800.00 $ 3,800.00 <br /> 140 TEMP PROTECTN/DIRECTN 1 LUMPSUM $2,500.00 $2,500.00 $ 3,000.00 $ 3,000.00 $ 2,930.00 $ 2,430.00 <br /> 150 FLAGGING 30 HOUR $50.00 $1,500.00 $ 133.39 $ 9,000.20 $ 84.00 $ 2,520.00 <br /> 160 FINAL TV INSPECTION & CLEANING 1 LUMPSUM $2,000.00 $2,000.00 $ 3,800.00 $ 3,800.00 $ 3,250.00 $ 3,250.00 <br /> 170 JOINT AIR TESTING 21" DIA. 25 EACH $250.00 $6,250.00 $ 80.00 $ 2,000.00 $ 533.00 $ 13,325.00 <br /> 180 GROUTING MAIN LINE 21" DIA. 23 EACH $700.00 $16,100.00 $ 285.00 $ 6,555.00 $ 100.00 $ 2,300.00 <br /> 190 GROUTING SET UP 21" MAIN 5 EACH $1,000.00 $5,000.00 $ 500.00 $ 2,500.00 $ 550.00 $ 2,750.00 <br /> Total: Alternate #1 $36,850.00 $ 22,705.20 $ 30,375.00 <br /> <br /> `GRAND TOTAL: $111,325.0 $83,463.20 97,548.00 <br /> <br />