far. This means we still have a gap of$171,463 that we'll need to identify to backfill and to get the project back to the <br /> appropriate SDC allocation percentage. I think this could have a significant impact in our capital project assumptions <br /> for this year so any additional information you could provide would be great. (or just tell me I'm misinterpreting this ...) <br /> Next, is Amazon <br /> Our current estimate for the project is about$774,000 and the current funding available is$597,485, leaving a gap of <br /> $176,515. Neil and I identified the CIP item that's for ADA improvements in parks and that accessibility improvements in <br /> Amazon Park would be 49%eligible for SDC monies from this pot. I've done some analysis on what we could cover with <br /> this money—and I think we could legitimately use about$185,000 of the available $450K. As such, I'd like to suggest the <br /> following breakdown: <br /> 321—Old Bond: $346,935 <br /> 336—ADA Fund: $185,165 <br /> 336-9—SDC Reimb.: $241,900 <br /> Total $774,000 <br /> We have an updated cost estimate coming our way on Friday which will be more detailed, but I don't think it will be <br /> more expensive. Let me know if this seems like a reasonable way to fund the project in full. <br /> Charnel Mulligan <br /> Our current estimate for this project is$676,250 and current funding available is$509,784 leaving a gap of$166,466. <br /> Again, I think we can use some ADA based SDC funding to cover some of the gap here, but not all. Here's my suggested <br /> funding breakdown for this project: <br /> 171—CDBG: $200,000 <br /> 187—Donations: $9,784 <br /> 311—General: $250,000 <br /> 336-9—SDC Reimb. $50,000 <br /> 336—ADA CIP: $95,880 <br /> Unknown fund: $70,586 <br /> Total $676,250 <br /> Last but not least, Neil mentioned that Kevin Foerstler's parking renovation project has gone over by quite a bit, but I <br /> don't see this reflected in the current project information. Can you shed some light on the expenses we're expecting to <br /> hit for the project? I see about$100,850 left in the project, but I assume you have more information than I do at this <br /> point. <br /> Thanks so much for whatever you know and can share, Lacey. <br /> Emily <br /> Emily Proudfoot, ASLA <br /> Landscape Architect,City of Eugene Public Works <br /> Parks and Open Space Division <br /> 1820 Roosevelt Boulevard <br /> Eugene,OR 97402 <br /> (541)682-4915 <br /> emilya.proudfoota,ci.eugene.or.us <br /> www.eugene-oraov/parks <br /> Find us on 114 <br /> 2 <br />