<br /> EUGENE SCHOOL DISTRICT 4J - MULTI -USE ATHLETIC FIELDS STUDY
<br /> PROJECT COST SUMMARY FEBRUARY 4, 1999
<br /> SUMMARY OF COSTS FOR EACH OPTION INCLUDED IN THE STUDY
<br /> OPTION 1 - SEPARATE FIELDS AT EACH HIGH SCHOOL
<br /> A B C D E F
<br /> BASIC BASIC FIELD ADD ADD ADD ALL
<br /> FIELD & UTILITY BLEACHERS ADDITIONAL RESTROOMS & FEATURES
<br /> COSTS SERVICES & LIGHTS COMPONENTS CONCESSIONS INCLUDED
<br /> CHURCHILL HIGH SCHOOL $1,178,017 $1,276,813 $1,603,976 $1,652,254 $2,099,410 $2,206,346
<br /> NORTH EUGENE HIGH SCHOOL $1,190,723 $1,268,418 $1,595,581 $1,643,859 $2,078,633 $2,141,900
<br /> SHELDON HIGH SCHOOL $1,168,143 $1,227,089 $1,549,327 $1,597,605 $1,987,466 $2,101,963
<br /> SOUTH EUGENE HIGH SCHOOL $1,121,010 $1,157,581 $1,479,819 $1,528,097 $1,899,673 $1,968,958
<br /> TOTAL COSTS FOR ALL FOUR HIGH SCHOOLS $4,657,893 $4,929,901 $6,228,703 $6,421,815 $8,065,182 $8,419,167
<br /> OPTION 2 - SINGLE FIELD
<br /> LOCATED AT THE KENNEDY MIDDLE SCHOOUCHURCHILL HIGH SCHOOL CAMPUS
<br /> A B C D E F
<br /> BASIC BASIC FIELD ADD ADD ADD ALL
<br /> FIELD & UTILITY BLEACHERS ADDITIONAL RESTROOMS & FEATURES
<br /> COSTS SERVICES & LIGHTS COMPONENTS CONCESSIONS INCLUDED
<br /> IF BUILT INSIDE EXISTING TRACK $1,299,677 $1,397,547 $2,123,025 $2,171,303 $2,680,272 $3,198,160
<br /> IF BUILT ON FIELDS SOUTH OF TRACK $1,242,276 $1,310,944 $2,031,497 $2,079,775 $2,625,894 $3,115,929
<br /> BASIC FIELD COSTS INCLUDE:
<br /> 1 FIELD ENGINEERING
<br /> 2 FIELD SURFACE AND DRAINAGE
<br /> 3 CHAIN LINK FENCE AND GATES
<br /> 4 PAVEMENT BETWEEN FENCE AND FIELD
<br /> 5 WALKWAY BETWEEN PARKING AND FIELD
<br /> 6 EMERGENCY AND SERVICE VEHICLE ACCESS
<br /> 7 TRACK AND FIELD AMENITIES REPLACEMENT
<br /> 8 GOAL POSTS
<br /> BASIC FIELD & UTILITY COSTS INCLUDE:
<br /> ALL OF THE ABOVE ITEMS 1 - 8 PLUS
<br /> 9 ADD FIRE WATER UTILITY SERVICE
<br /> 10 ADD ELECTRICAL UTILITY SERVICE
<br /> ADDITION OF BLEACHERS AND LIGHTS INCLUDE:
<br /> ALL OF THE ABOVE ITEMS 1 -10 PLUS
<br /> 11 ADD 1000 SEAT GRANDSTAND
<br /> 12 ADD ELEVATOR TO OBSERVATION BOOTH
<br /> 13 ADD FIELD LIGHTING
<br /> ADDITIONAL COMPONENTS INCLUDE
<br /> ALL OF THE ABOVE ITEMS 1 -13 PLUS
<br /> 14 ADD SCORE BOARD
<br /> 15 ADD ACOUSTICAL SOUND SYSTEM
<br /> 16 ADD DUMPSTER STORAGE AREA
<br /> ADDITION OF RESTROOMS AND CONCESSIONS INCLUDE:
<br /> ALL OF THE ABOVE ITEMS 1 -16 PLUS
<br /> 17 ADD RESTROOM FACILITIES
<br /> 18 ADD CONCESSION BUILDING
<br /> 19 ADD SANITARY SEWER UTILITY SERVICE
<br /> 20 ADD DOMESTIC WATER UTILITY SERVICE
<br /> •
<br /> ALL OF THE PROPOSED FEATURES INCLUDE:
<br /> ALL OF THE ABOVE ITEMS 1 -20 PLUS
<br /> 21 ADD WALKWAY LIGHTING BETWEEN PARKING AND FIELD
<br /> WBGS ARCHITECTURE PLANNING PC 2/4/99
<br /> PROJECT COST SUMMARY PAGE 1