O <br /> Budget based on award to Bones (Avery) with ALL park components <br /> BASIS OF AWARD PKG D included in engineer's final (X) Contractor B <br /> budget estimate selection CHOICE Bid <br /> Base Bid $ 3,753,537 $ 4,000,896 $ 3,458,468 X $ 3,458,468 <br /> ADD electrical components at bleachers $ 110,272 $ - $ 97,373 <br /> DELETE park lighting $ (75,137) $ - $ (36,353) <br /> DELETE play equipment @SHS $ (56,417) $ - $ (40,044) <br /> DELETE tennis improvements $ (21,600) $ - $ (8,906) <br /> DELETE picnic shelter @SHS $ (36,875) $ - $ (28,527) <br /> ADD 28' to SHS basketball court $ 15,100 $ 10,707 x $ 10,707 <br /> DELETE west side paths @CHS $ (28,710) $ - $ (1,517) <br /> DELETE bleacher fencing $ (28,620) $ - $ (19,069) <br /> ADD sand channel drainage $ 215,215 $ 215,215 $ 194,302 x $ 194,302 <br /> PKG A - SYNTHETIC TURF - ALTERNATES <br /> soccer lines w/ heavy backing $ 65,570 $ 65,570 x <br /> football lines w/ heavy backing $ 56,030 $ 56,030 x <br /> PKG C - FIELD LIGHTS <br /> field lighting 1 $ 248,000 I $ 248,000 I x <br /> PKG B - BLEACHERS <br /> bleachers -6', 9/1 &10/1 $ 655,000 $ - <br /> foundation for future roof $ 49,000 $ - <br /> deduct for 4' cross isle height $ (33,500) $ - <br /> deduct for open deck system $ (32,800) $ - <br /> TOTAL OF ABOVE ITEMS: $ 3,968,752 $ 4,033,077 <br /> BUDGET AVAILABLE FOR ABOVE: $ 4,047,180 $ 4,047,179 <br /> BALANCE: $ 78,428 $ 14,102 <br /> PKG A - SYNTHETIC TURF - BASE BID <br /> turf - basic w/ bond $ 1,520,958 $ 1,520,958 <br /> add for heavy backing w/ bond $ 151,283 $ 151,283 <br /> additional drainage $ 66,000 $ 66,000 <br /> Non construction (soft costs) (FIXED) $ 1,293,880 $ 1,293,880 <br /> construction contingency (FIXED) $ 570,699 $ 570,700 <br /> PARKS COMPONENTS: <br /> Park elements $ 1,929,640 1,885,824 <br /> Soft costs (fixed) $ 542,550 $ 542,550 <br /> Construction Contingency (fixed) $ 192,964 $ 192,964 <br /> TOTAL: $ 2,665,154 $ 2,621,338 <br /> FIELDS COMPONENTS: <br /> Items in the base bid - pkg D $ 2,039,111 1,777,653 <br /> Synthetic Turf $ 1,738,241 $ 1,738,241 <br /> Turf Alternates $ 121,600 <br /> bleacher /light alternates $ 248,000 <br /> Soft costs (fixed) $ 751,331 $ 751,331 <br /> Construction Contingency (fixed) $ 377,735 $ 377,735 <br /> TOTAL: $ 4,906,418 $ 5,014,560 <br /> Grand Total: $ 7,571,572 $ 7,635,898 <br /> budget $ 7,650,000 $ 7,650,000 <br /> available $ 78,428 $ 14,102 <br />