Draft CONSTRUCTION COST ESTIMATE <br /> City of Eugene Parks & Open Space Planning <br /> PROJECT: Owen Rose Garden Phase II <br /> CAP. PROJ. #: <br /> DATE: 5.3.07 <br /> PM: Hostick <br /> 'Cost Summary t <br /> Contracted Construction <br /> Heritage Rose Area Renovation $ <br /> Main Path Improvements $85,500 <br /> Art and Ornamentation $50,600 <br /> Subtotal $233,077 <br /> Construction Contingency110.0% 1 $23,308 <br /> Total estimated Construction Cost' $256,3841 <br /> Subtotal <br /> Item Quantity Units Material Cost Labor Cost Mtrl & Labor Comments <br /> HERITAGE ROSE AREA RENOVATION <br /> Tree protection 500 If 0.50 0.75 $625 . <br /> Erosion control 1 sum 250.00 1,000.00 $1,250 . <br /> Import soil 1,000 cy 25.00 0.00 $25,000 . <br /> Rough grading 36,000 sf 0.00 0.13 $4,680 <br /> Fine grading 20,000 sf 0.00 0.15 $3,000 . <br /> Paths $39,470 <br /> Geotextile 16,000 sf 0.05 0.10 $2,400 . <br /> 3/4" rock (4 ") 200 cy 20.00 5.00 $5,000 . <br /> 1/4" rock (2 ") 100 cy 25.00 5.00 $3,000 . <br /> Steel edging and stakes 3,800 If 4.40 3.25 $29,070 . <br /> Drainage . <br /> 4" pvc drain line 120 If 3.00 9.00 $1,440 . <br /> area drain 0 ea 0.15 0.00 $0 . <br /> trench drain w /rock 100 If 1.00 5.00 $600 . <br /> Irrigation . <br /> Heritage rose lawn strip 3,000 sf 0.10 0.50 $1,800 <br /> Heritage rose beds 20,000 sf 0.10 0.50 $12,000 <br /> Equipment mobilization and staging 1 sum 0.00 8,986.50 $8,987 . <br /> Total $96,977 <br /> MAIN PATH IMPROVEMENTS (options) <br /> Concrete paths, 5.5" thick (colored) 11,400 sf 4.00 3.50 $85,500 <br /> Total $85,500 <br /> ART AND ORNAMENTATION <br /> Omamental ironwork gateways 3 sum 0.00 8,000.00 $24,000 . <br /> Cast iron light standards 4 sum 2,000.00 1,000.00 $12,000 . <br /> Art (scope not identified) 1 sum 0.00 10,000.00 $10,000 <br /> Interpretive panel 1 ea 1,100.00 3,500.00 $4,600 <br /> Total $50,600 <br /> Heritage Paths <br /> Gravel w /steel edging 16,000 sf 0:75 1.75 $40,000 <br /> Gravel w /concrete edge 16,000 sf 1.25 2.25 $56,000 <br /> Concrete paths, 5.5" thick 16,000 sf 1.85 3.50 $85,600 . <br /> Concrete paths, 5.5" thick (colored) 16,000 sf 4.00 3.50 $120,000 . <br /> Concrete paths, 5.5" thick (colored + stamped) 16,000 sf 4.00 5.50 $152,000 <br /> Natural basalt stone path 16,000 sf 4.50 18.00 $360,000 <br /> Main Path <br /> Steel edging only 1,000 If 4.40 3.25 $7,650 <br /> Concrete mow strip only 1,000 If 1.85 12.00 $13,850 <br /> Concrete paths, 5.5" thick 11,400 sf 1.85 3.50 $60,990 <br /> Concrete paths, 5.5" thick (colored) 11,400 sf 4.00 3.50 $85,500 <br /> Concrete paths, 5.5" thick (colored + stamped) 11,400 sf 4.00 5.50 $108,300 <br /> Natural basalt stone path 11,400 sf 4.50 18.00 $256,500 <br /> • <br /> Hawkins View Park . Page 2 of 3 5/10/2007 <br />